A landowner pressures the FWM to start a harvesting operation immediately to meet a tight deadline. The site has steep slopes and a public footpath, but no site-specific risk assessment or safety plan has been completed. The crew is on standby and the landowner insists they “figure it out on the go.” What should the FWM do first?

Multiple Choice

While planning a thinning operation, the FWM learns there is an overhead power line crossing a corner of the coupe. The contractor suggests just “being careful” to avoid delays. How should the FWM address this hazard?

Multiple Choice

The FWM needs to hire a contractor for a large felling operation. One bidder is cheaper with a poor safety record and old equipment; another costs more but has a strong safety reputation and maintained machines. What is BEST?

Multiple Choice

A small crew will carry out manual felling. One member is a new hire with no formal qualifications; the contractor says he’s learned on the job. What should the FWM do?

Multiple Choice

Midway through a harvesting operation, the FWM sees a chainsaw operator working without leg protection (chainsaw trousers) due to heat. The contractor is behind schedule and relaxed PPE rules. What is MOST appropriate?

Multiple Choice

A harvesting site has a popular hiking trail crossing the work area for two weeks. On inspection there are no warning signs/barriers where the public could enter the felling zone. What should the FWM ensure next?

Multiple Choice

Remote site with poor phone coverage. Before work, the contractor admits no formal emergency plan is in place. What should the FWM require?

Multiple Choice

A week-long planting job has no nearby facilities. Contractor arranged no welfare, arguing it’s short and workers can use the woods and eat in vehicles. What is the CORRECT approach?

Multiple Choice

Large site with felling, forwarding, and lorry loading. A lorry arrives early and drives near active felling. How should the FWM have prevented this overlap?

Multiple Choice

Contractor proposes using chainsaw operators with only basic quals to fell very large diseased trees near a road. What is BEST?

Multiple Choice

Clear-fell adjacent to a busy public road; trees could reach traffic if uncontrolled. What should the FWM implement?

Multiple Choice

Forest maintenance task: worker spraying herbicide alone in a remote area with no cell reception. What should the FWM do?

Multiple Choice

Severe storm with high winds is forecast mid-week. Contractor wants to keep working to stay on schedule. What should the FWM do?

Multiple Choice

Landowner gives direct instructions to crew, asking for an extra tree near a power line not in the plan, for “the view.” Crew feels pressured. What should the FWM do?

Multiple Choice

Loaded forwarder nearly tipped on a slope; no injury/damage. Contractor says it’s “just a close call” and wants to continue. What should the FWM do?

Multiple Choice

Contractor proposes using an old skidder with no ROPS while the newer machine is in repair; operator promises to be careful on slopes. What should the FWM do?

Multiple Choice

On arrival, FWM sees that ‘Forestry Operations – Keep Out’ signs at a public access point have blown down. Active chainsaw and machinery work is ongoing. What is the immediate duty?

Multiple Choice

During logging, a felled tree gets hung up in another. The crew wants to bring it down quickly. As FWM, what must you insist on?

Multiple Choice

Harvesting is next to a river on uneven ground, with risk of sliding toward water in wet conditions. What precautions should the FWM implement?

Multiple Choice

Crew working 10-hour days for a week show fatigue; a minor felling error occurred. Deadline is close and contractor wants another long day. What should the FWM do?

Multiple Choice

FWM can’t be onsite daily for a high-risk felling job. How should supervision be ensured?

Multiple Choice

A lorry driver arrives without PPE and walks into the stacking area. What is the correct action for the FWM?

Multiple Choice

New worker arrives mid-project with basic gear but no site-specific induction. Contractor wants him to start immediately. What should the FWM do?

Multiple Choice

A subcontractor repeatedly ignores safety protocols (no PPE, bypasses checks) despite reminders; main contractor hesitates to discipline due to productivity. What should the FWM do?

Multiple Choice

Thinning team has two sawyers and a forwarder working concurrently in the same area, putting people on foot near machinery. What is proper FWM approach?

Multiple Choice

Main contractor brings a sub-contractor crew not in initial briefings, with different practices. What should the FWM do?

Multiple Choice

After hours, stacked timber is near a public road and an access gate is partly open. How should the FWM manage off-hours safety?

Multiple Choice

Mid-operation, a harvester finds an old unsecured mine shaft near a harvesting zone. Serious fall hazard; landowner never mentioned it. What must the FWM do?

Multiple Choice

A machine operator smells of alcohol and appears sluggish; contractor is short-staffed and wants to keep him working. What should the FWM do?

Multiple Choice

A serious accident: a falling tree injures a worker with a complex fracture. Contractor wants to resume next day and “handle internally.” What are the FWM’s obligations?